A busy office that required extensive modifications to the office space over a 2 day period.

  • Client: Interserve
  • Construction Year: 2017
  • Location: Earlsdon Park, Coventry, UK
  • Duration: 2 Days
  • Category: Local Authority & Govenment

The Department of Education required the glazed partitions on their 5th floor to be removed to create an open plan office area.

The works were carried out over a weekend, with 2 gangs of labour working over the entire weekend, starting at 6pm on the Friday and finishing at 10pm on the Sunday.

All making good was carried out to existing plasterboard partition walls and carpet tiles replaced where the previous partition floor track was.