These works involve replacing an existing 30+ year old motor control panel with a new custom built MCCB panel board with PLC control.

This board controlled the Airhead LV infrastructure and in the event of an incident on the Airhead a load shed-ding sequence was integrated into the initial design to switch off the non-essential loads to provide enough power to run two deluge pumps to ensure fuel was safely removed from the storage tanks.
  • Client: Interserve Defence Limited
  • Construction Years: Oct/Nov 2019
  • Location: Ascension Island, South Atlantic
  • Duration: 6 Weeks
  • Sector: Private

Comments are closed.